Position:
        Senior Engineer                                       
GF2 web
Location:
        Wakefield                       
Date of Birth:
        7th June 1962                                             
Education:
  • B Eng. (Hons) Mechanical Engineering
  • Higher Tec Certificate in Mechanical and Production Engineering
  • Tec Certificate in Mechanical and Production Engineering
  • Member of Institution of Mechanical Engineers   

Training and CPD:
  • NEC3: PSC Training - March 2010
  • Design Risk Management
  • CCNSG Safety Passport - 2 Day course
  • Training on the Bosch Rexroth Systems and Engineering

Career History:
  • FTL Co Ltd (1978-1983) Design Engineer of stainless steel hose assemblies
  • Moved to Oilgear Towler Ltd (1987-1990) as a Design Draughtsman for the design of hydraulic power units/manifold blocks.  Promoted to Applications Engineer after 12 months where duties involved circuit design and component selection.
  • Adamson Green Ltd (1990-1991)  Application/Sales Engineer responsible for internal sales and quotations.
  • Hedley Hydraulics Ltd (1991-1993) Sales Engineer responsible for sales of hydraulic equipment in North Midlands area.
  • Pressure Design (1993-2000) Sales and Project Engineer responsible for handling project work from enquiry to commissioning.  Servicing of existing customer base with regard to plan modifications and troubleshooting.  Also supervision of drawing office personnel.
  • Qualter Hall & Co Ltd (2001-2003) Senior Hydraulics Engineer responsible for handling project works from enquiry to commissioning including preparation of tenders, system design, liaising with suppliers and on site commissioning.
  • Bosch Rexroth (2003-2009) Sales Manager Northern Region responsible for sales of hydraulic components and systems from enquiry to order stage. 
  • Joined Kenneth Grubb Associates in 2009 as Senior Engineer.

Relevant Project Experience - Kenneth Grubb Assoicates Ltd

 

Hull Tidal Surge Barrier Refurbishment
This is a prestigious Environment Agency Project for the future protection of Hull.  The gate is 30m span x 10.6m deep and weighs 212 tonne.  The project includes refurbishment of the hoisting system to include modern hydraulic drives and a gravity close feature to improve the reliability of the Barrier.  KGAL were commissioned by Halcrow to project manage and technically review this EA Design and Build project.  My responsibility includes reviewing the Hydraulic Designs produced by the main contractor and undertaking a Hazop Study into the various modes of operation.

Dartford Creek Barrier Refurbishment
The Dartford Creek flood barrier consists of 2 vertical wheel gates, each 30m span by 5.2m high, designed to stack vertically, one on top of the other, to give when closed a total flood protection depth of 10.4m above the gate sill.  Each section, weighing approximately 160 tons is raised and lowered utilising high tensile steel transmission chains powered from counterweight assisted hydraulic motor / gearbox drive assemblies.  KGAL were commissioned to project manage and technically review this EA Design and Build project.  My involvement was initially to assist with the commissioning of Phase 1 of the project which involved replacing the Chains.  This involved utilising the existing hydraulic equipment which was originally supplied in 1987.  Phase 2 which is due for completion in 2010 is to replace the Hydraulic and Electrical control systems and I was involved in the Tendering process up to contract award.

Pont-Y-Werin Bridge
KGAL were retained by Dean & Dyball Ltd to undertake the M&E system designs for a hydraulically driven single-span foot / cycle track bascule bridge on the River Ely at Cardiff harbour.  My involvement was to undertake preliminary design work on the hydraulic system which was then developed by the Hydraulic Contractor.

Bristol City Council, Cumberland Basin Mitre Gates and Controls Replacement
Cumberland Basin is a flood defence and boat lock system consisting of two sets of mitre gates, two sets of penstocks and a swing bridge.  The existing system uses a pumped water system to operate.  The system was originally installed by I.K Brunel.  My involvement was to design the Hydraulic System for Phase 2 of the project to operate the Gates and Sluices at Entrance Lock, undertake Factory Acceptance Testing of the equipment and assist with commissioning.

Media City Pedestrian Footbridge
The project was to construct a new opening type pedestrian footbridge at Salford Quays to link the South East side of the Manchester Ship Canal to the North West where the Media City development is to be located.  The bridge rotates 71 degrees about a pier mounted pivot point to allow vessels to pass through the channel using a Hydraulic Motor / gearbox drive assembly.  KGAL were retained by Balfour Beatty to undertake the M & E system designs and provide a Hydraulic Simulation of the Bridge Operation.  My involvement was to initially design the hydraulic system and then to prove its suitability to operate the Bridge under all the Design Load conditions using Simulation software.

Relevant Project Experience - Qualter Hall & Co Ltd

Dublin Berth 26 Linkspan
Berth 26 is a double deck linkspan raised and lowered using electric drive winches.  Upper and lower deck separation can be varied using hydraulic cylinders to enable a variety of different vessels to use the berth.  The upper deck is fitted with finger flaps operated using hydraulic cylinders to lower onto the upper deck of the vessel.  Responsible for overseeing the design, factory acceptance testing (FAT), installation commissioning and sat testing of the complete hydraulic system.

Cardiff Queen Alexandra Docks - Lock Refurbishment

I was involved in the site installation and commissioning of replacement hydraulic power units, cylinders and pipe work to operate the mitre gates and sluices on the above project.

Whitby Swing Bridge Refurbishment
The bridge provides a very important link across the harbour in the centre of Whitby and has to be opened for vessels for a period of two hours either side of high tide.  Responsible for the design, FAT, installation, commissioning and site acceptance testing (SAT) of new hydraulic power units as part of the refurbishment.  A standby diesel engine was incorporated into the design to provide a full standby facility in the event of a mains power failure.  The bridge was kept operational during the works.

Selby A19 Swing Bridge Refurbishment
Selby Swing Bridge is a road bridge crossing the River Ouse at Selby.  I was responsible for the design, FAT, installation, commissioning and SAT of a new hydraulic system to operate the jacking and nose bolt cylinders.  This work had to be undertaken whilst keeping the bridges operational.

Humber Sea Terminal Berth 3 Linkspan
Humber Sea Terminal is a Ro Ro Terminal on a floating pontoon providing a deepwater off-loading facility free from tide restraints and lock systems.  I was responsible for modifying the existing hydraulic system to operate the New Berth 3.

Relevant Project Experience - Pressure Design

Selby Canal Swing Bridge
Mechanical and hydraulic design of an operating mechanism to open and close a swing bridge over the Selby Canal.  The bridge was originally designed for manual slewing with a hand pump to operate the jacking wedges.  I designed a linkage mechanism operated via a hydraulic cylinder which fitted underneath the bridge to automate the slewing operation and a new hydraulic power unit to provide the necessary power.

Hillhead Swing Bridge - Forth and Clyde Canal
Erskine Ferry Swing Bridge - Forth and Clyde Canal
Twechar Lift Bridge - Forth and Clyde Canal
These three bridges over the Forth Clyde Canal in Scotland were refurbished as part of its re-opening as a millennium project in 1999/2000.  the canal had been closed since 1961 and the bridges required extensive renovation including complete new operating systems.  I was involved in the design, manufacture, installation and commissioning of the hydraulic power units and cylinders.

Bell Weir Lock Gates - River Thames
Romney Lock Gates - River Thames
I was responsible for the design, manufacture, installation and commissioning of new control pedestals to replace the existing obsolete units.  The new pedestals had to be designed to be operated safely by both lock keepers and the general public as well as having an emergency hand operation facility.  The complete installation had to be carried out during a two week canal closure.

Pembroke Ro-Ro Ferry
The ferry terminal was upgraded from a single deck to a double deck arrangement.  I was involved in the design, manufacture, installation and commissioning of a new hydraulic system to operate the additional cylinders on the upper deck finger flaps, as well as replacing the existing hydraulic system which operated the lower deck.  The new equipment had to be installed and commissioned whilst maintaining the full operation of the lower deck to allow ferries to dock at twelve hour intervals.

Relevant Project Experience - Oilgear Towler Ltd

Cawood Swing Bridge
Replacement of hydraulic and electrical control system on swing bridge over River Ouse at Cawood.  I was involved in the design of the new hydraulic system.

 
 
 
Home
Ports & Marinas
Flood Defence
Hydro Power
Moving Bridges
Special Projects
About Us
Company History
The Team
Career Opportunites
Technical Papers
Contact Us
Newsletter
Copyright © 2010 KGAL                                                                                                                            
Site Map
www.intergage.co.uk | Web Design in Dorset