Bulkhead gates, Cruachan

 

Cruachan Dam

Enterprise Engineering Services Ltd were awarded a contract by Scottish Power to remove and refurbish the two Bulkhead Gates at Cruachan Dam in Scotland.

Kenneth Grubb Associates Ltd were asked to design a replacement bulkhead gate structure. In addition, the client also required a remote winching system for the watertight access cover, a remote gate spragging system and a new access walkway for the bulkhead gate storage bay.

KGAL were given the brief that the new designs had to be fully interchangeable with the existing civil structure.

KGAL developed the new designs, analysed the structures, detailed the designs and supplied a full set of manufacturing data to EESL.

The gate was fabricated in four modular sections at EESL's Aberdeen facility, transported to site and installed. Both the walkway and gate spragging system were fabricated, hot-dip galvanized and installed on site. The winching system was procured by EESL based on design work carried out by KGAL and installed on site.

 
 
1
Glendoe hydro scheme
Rannoch Weir
Radial gates refurbishment at Aigas and Kilmorack
Automatic tilting weir gates, Bonnington
Stainless steel smolt screen, Cassley Intakel
Bulkhead gates, Cruachan
Radial gates, Derbendi-Khan
Fishbelly gate design, Dolgarrog
Radial gates, Dundreggan
Intake gates, Earlstoun
Replacement trash screen, Invergarry
Water control Gates at Nathpa
1
 
Home
Ports & Marinas
Flood Defence
Hydro Power & Dams
Trashracks & Screens
Radial Gates
Wheel Gates
High Pressure Slide Gates
Stoplogs
Hydro Turbines
Moving Bridges
Careers
About Us
News

© 2012 KGAL - Mobile Version

www.intergage.co.uk